Slide 42 of 61
Notes:
Please refer to figure A.4 on page 610 of the textbook for the following descriptions (the authors apologize that the figure is not available at this time). Figure A.1 is presented as a slide and can be used as as suitable replacement for discussion purposes.
Each rectangle is divided into sections. The task name is at the top. The task ID and the estimated duration are in the middle section of the rectangle. The start and end dates, which are automatically calculated by Project are in the lower section of the rectangle.
Primitive tasks (only) are connected by arrows the indicate predecessors and successors. This information, if recorded on the Gantt Chart, is carried over to the PERT Chart.